Jordan and Elbridge Freeze a $567,216 Contractor Payment as Their $30.4 Million Water Overhaul Enters Its Final Stretch

9 min read
The Main Street commercial block in the village of Jordan. Contract 2 water main and service work ran beneath North and South Main streets, according to the joint boards' 2026 minutes. (Photo: Googoo85 / Wikimedia Commons, CC BY-SA 3.0)
In this story
    In this story

      Every foot of new water main is in the ground seven years after the joint project began. Now the budget tracker shows $31.18 million in costs against a $30.4 million bond, a bond increase lands on all three August board agendas, and the boards are holding a $567,216.68 payment until the contractor produces a street by street schedule.

      The three municipalities that share a single water system, the villages of Jordan and Elbridge and the town of Elbridge, have spent seven years and are now on track to spend more than $31 million rebuilding it. On July 21, 2026, the joint water board that oversees the project voted to hold up the single largest payment request of the summer: $567,216.68 owed to Highlander Construction Inc. for water main and street restoration work under Contract 2. The money will stay in municipal accounts until the contractor produces something the boards say they have been asking for: a schedule that lists an end date for every street it has torn up.

      This story came from public records we pulled ourselves

      Get the next one, plus overnight incidents, in your inbox at 6 AM. Free, no spam.

      According to the unofficial minutes of that meeting, recorded by Town of Elbridge Clerk Patti Cooper, the motion to withhold Payment Application No. 13 came from Councilman Todd Platten and was seconded by Supervisor Kenneth Bush III. The minutes describe the reasoning directly: “All three municipalities to HOLD payment for Application #13 until Highlander can provide a schedule that has end dates for each street.” The recorded roll call, 3 ayes and 0 nays, reflects the Town of Elbridge board members in the room that day: Bush, Platten and Councilman Joe Farrugia. The resolution language itself extends beyond the Town, directing that “all three municipalities” hold the payment, and Village of Elbridge Mayor Christopher DeCola and Village Clerk Tammy Kunz are both listed among those present for the discussion.

      It was not a one-time complaint. The minutes note that the boards had already withheld a payment application once before over the same missing schedule, and record a running list of smaller grievances municipal officials plan to route to project engineer Ian Douglass at Barton & Loguidice, the firm managing construction. Village of Elbridge Mayor Christopher DeCola and Clerk Tammy Kunz agreed to relay complaints from Elbridge; Platten agreed to do the same for the Town of Elbridge and Village of Jordan. Two specific items made the July minutes: the placement of an air relief valve vent near the community garden and on Mechanic Street in Jordan, and a decision to blacktop in front of the library rather than restore the brick sidewalk that was there before construction crews arrived.

      Jordan-Elbridge Joint Water Project, by the numbers Source: July 21 and May 19, 2026 joint water board minutes; Nov. 7, 2024 project fact sheet $30.4M Bond approved by all three municipalities $31.18M Project budget to date, per tracker -$782,237 Contingency shortfall as of May 19, 2026 $567,216.68 Contractor payment on hold since July 21 10 miles Water main, all now reported installed 7 years Since project start in 2019 CNY Signal analysis of joint water board records, Aug. 7, 2026.

      The payment fight is unfolding as the physical work nears its finish. Contract 2, the Highlander-built distribution piping that runs beneath North and South Main Street in Jordan and through much of the Village of Elbridge, was listed at 93 percent complete in the July 21 minutes, up from 83 percent in mid-May and 73 percent in late April. The same minutes report a milestone for the whole project: “All water main is installed.” What remains on Contract 2 is narrower: two water services left to connect on Jordan Road, pressure-reducing valve vaults still being set at the Champions Mobile Home Park connection, and street-by-street restoration, the exact work the boards want scheduled before they release the withheld payment.

      The other two construction contracts are close behind. Contract 1, the distribution and pump station work being built by R.B. Robinson Contracting Inc., stood at 90 percent complete, with a $198,330 payment approved at the July meeting. Contract 3, the water storage tank work built by Statewide Aquastore, was also listed at 90 percent complete with no payment application pending. Four pieces of tank and pump station equipment were still moving through fabrication and delivery as of July 21: one tank was in production for delivery the week of August 24, a second for the week of October 26, a third for the week of December 1, and a fourth for late December or early January. A separate storage tank on Brutus Road was closer to done, awaiting only a pressure test on its outlet pipe before it can go online, according to the minutes.

      None of that is cheap, and the project’s own numbers show it is now running ahead of what voters in all three municipalities approved to borrow. A detailed budget tracker attached to the May 19, 2026 joint board minutes lists total project budgets to date at $31,182,237.06 against total project bonding of $30,400,000.00, a $782,237.06 shortfall the tracker labels, bluntly, as negative remaining contingency. The tracker breaks the number down by contract: Contract 1A work by R.B. Robinson at $12,161,095.47 including an estimated Jordan Road main replacement and final reconciliation costs; Contract 1B tank work by Kahrs Construction LLC at $413,000; Contract 2 work by Highlander at $10,840,296.09; Contract 3 tank construction by Statewide Aquastore at $2,962,000; and $4,805,845.50 in engineering, legal, bond counsel, land acquisition and fiscal advisory costs.

      The same May 19 minutes show the boards weighing how to close that gap. Engineering firm Barton & Loguidice laid out contingency scenarios ranging from doing no additional work, which the tracker priced at a positive $1,148,112.94 in remaining room, to replacing the Jordan Road water main and building a new tank on Jordan Road, which the tracker priced at negative $772,237.06. The boards chose the more expensive path. The minutes record: “Project will move forward with replacing Jordan Road Water Main & New Tank,” and note in the same breath that the group decided against a separate looping project near the Meadows development, and that “a bond increase will need to be completed.” Barton & Loguidice agreed to prepare user cost estimates for each municipality ahead of that vote.

      Project spending has passed the bond that funds it Budget tracker attached to May 19, 2026 joint board minutes $30.40M Bond approved $31.18M Budget to date $782,237 over Bars scaled to dollar totals; gap of $782,237.06 flagged by the tracker as negative contingency.

      That bond increase is now formally teed up. The July 21 minutes list “Bond Increase to be put on August Agendas” as an action item, with Barton & Loguidice preparing a handout for each of the three board meetings this month. Village, town and joint water board officials will need to act on the increase separately, since each municipality issued its own share of the original bonding, before the added Jordan Road tank and main work can be locked into the budget without further contingency draws.

      Change orders are adding to the pressure on both major contracts. Contract 1’s potential change order log shows $212,829 submitted against a $200,000 miscellaneous allowance, with $107,256.46 accepted and $92,743.54 in balance remaining; a $26,500 railroad services change order was still pending a decision as of July, with the boards opting to wait until August. Contract 2’s change order log is larger: $523,958.19 in potential change orders submitted against a $180,000 allowance, with $177,628.90 accepted, a $50,000 separate change order already issued, and $52,371.10 left in balance. A $21,442.03 change order covering a water service dispute involving a DeMarco property on the route was also pushed to the August meeting.

      The project traces back to infrastructure that all three municipalities agreed, in a State Environmental Quality Review filing with the state Department of Environmental Conservation in July 2023, needed to be replaced: small diameter and dead end water mains, asbestos cement and galvanized steel pipe, and insufficient fire flows across the shared system. A project fact sheet dated November 7, 2024 and posted by the Village of Jordan lays out how the current plan grew from that filing. The project started in 2019, finished design work in 2024, and began construction on October 10 of that year, with completion estimated for 2027. The scope: about 10 miles of replacement water main, valves and hydrants; a new 360,000-gallon tank and pump station at the City of Syracuse connection; a new 200,000-gallon tank and pump station on Hamilton Road; a new 105,000-gallon tank on Hamilton Road near Brutus Road; and a new Crossett Road pump station paired with a Jordan Road chlorine booster station.

      From 2019 start to a 2026 payment freeze 2019 Joint water project begins July 2023 DEC SEQR filing flags aging, asbestos-cement mains Oct. 10, 2024 Construction begins after design completed May 19, 2026 Budget tracker shows $782,237 shortfall July 21, 2026 Boards vote to hold $567,216.68 payment August 2026 Bond increase goes to all three boards 2027 (est.) Target construction completion

      That fact sheet also shows how the project is financed. Of the $30.4 million estimated cost, $17.25 million comes from grants: a $2.25 million congressionally directed spending grant, $5 million Water Infrastructure Improvement Act grants apiece for the Town of Elbridge and Village of Elbridge, and a combined $5 million for the Village of Jordan split between a $2 million WIIA grant and a $3 million Drinking Water State Revolving Fund grant. The remainder is bonded debt, which the fact sheet estimated would cost the average household $328 a year, down from an earlier 2022 estimate of $351.

      Residents in both villages got a reminder this month that a project this size does not run without friction, even on the billing side. On August 3, 2026, Village of Jordan Mayor Casey Brim sent a letter to water customers after a late notice about water bills went out in error the week before. “This was sent in error, it is not common practice for the Village of Jordan to send out late notices to village residents or a ‘Reminder’ regarding your water bill,” Brim wrote, explaining that the village only mails a water bill letter at the end of the fiscal year, when unpaid charges are levied onto a resident’s tax bill, and does not shut off water service over nonpayment. The letter drew a distinction for Town of Elbridge residents in the permissive area Jordan also serves: because Jordan cannot levy unpaid water charges onto Town of Elbridge tax bills, those customers can receive a delinquency notice and, in some cases, a shutoff notice. “I sincerely apologize for the confusion and the unnecessary fear of your water service being interrupted,” Brim wrote, adding that the billing department would be addressing what she called “this lapse in judgement.”

      Brim is also a regular presence at the joint water board table; the May 19 attendance list for Joint Board Meeting #17 names her alongside DeCola, Bush, Platten and representatives from Barton & Loguidice and Fiscal Advisors & Marketing. The overlap shows how tightly the billing side and the construction side of this project are now running together heading into August, a month when three separate boards are due to vote on a bond increase for tank and main work on Jordan Road, decide on pending change orders for both major contracts, and revisit whether Highlander has finally produced the street-by-street schedule that would release the $567,216.68 still sitting unpaid.

      Villages of this size, Jordan counted 1,192 residents and Elbridge 921 in the 2020 census, rarely carry water projects north of $30 million on their own. The three-way cost split baked into every payment application, with the Town of Elbridge covering 42.4 percent, the Village of Jordan 30 percent and the Village of Elbridge 27.6 percent of every dollar paid to contractors, reflects that reality: none of the three governments could have financed this system alone, and none can walk away from the shared bond now that the budget tracker shows the project running $782,237.06 past what voters approved.

      Sources and verification

      Every fact in this article was checked against primary documents and official records, including: img1.wsimg.com, dec.ny.gov, auburnpub.com, en.wikipedia.org. Direct quotes are verbatim from the cited documents.

      Know someone who should see this?

      Every share helps CNY stay informed. Post it to your neighborhood group, text it to a friend, or drop it on Reddit.

      C

      Staff Reporter

      CNY Signal News Team

      Reported and edited by the CNY Signal newsroom in Syracuse, New York. AI assisted, human edited.