A Developer Wants to Build 484 Homes on 89 Acres in Lysander, and the County Says the Parking Count Is Missing
Melvin Farms would add 176 townhouses, 168 apartments and 140 senior units off North Hayes Road. County planners attached three modifications, including turning lanes the state wants built before anyone can move in.
The largest housing proposal to reach the Onondaga County Planning Board this summer is not in Clay or DeWitt. It is in Lysander, on farmland off North Hayes Road, and it would add 484 dwelling units in one development.
This story came from public records we pulled ourselves
Get the next one, plus overnight incidents, in your inbox at 6 AM. Free, no spam.
The board reviewed the site plan on August 5 as case Z-26-184 and recommended modifications, which is the middle outcome in county planning review. It is not approval and it is not rejection. It is a list of things the town must handle before it approves anything.
Three of those things involve roads and sewers. A fourth item, buried in the staff report rather than the resolution, is that the county could not tell how many parking spaces the project would have.
### What 484 units actually looks like
The county staff report breaks the project down by building type, and the arithmetic is worth seeing laid out.
There would be 44 townhouse buildings holding four dwelling units each, for 176 units. There would be 24 apartment buildings holding seven units each, for 168 units. And there would be four senior apartment buildings holding 35 units each, for 140 units.
That totals 484 dwelling units.
The site is two vacant parcels totaling 104 acres with frontage on both North Hayes Road, which is County Route 157, and Cold Springs Road, which is New York State Route 370. The residential portion under review covers 89 acres of that.
The layout splits into two parcels. The townhouses sit on one 55.4 acre parcel. The apartment buildings, the senior apartments and a clubhouse sit on another 33.7 acre parcel. The staff report says no further subdivisions are anticipated.
An internal road loops the site, separating the townhouse area from the apartment area from the senior apartment area. The townhouse buildings line that internal road, backed by the apartment buildings, with the senior buildings arranged in the southern portion near North Hayes Road. The clubhouse is in the western portion, between the apartment and townhouse areas.
The preliminary site plan the county reviewed is dated November 2025.
### The wider project has a name and a bigger footprint
The staff report ties this to a larger development. An Environmental Assessment Form dated October 1, 2024, submitted with an earlier referral, describes the whole Melvin Farms development, including land across North Hayes Road, as resulting in 172 acres disturbed.
So the 89 acres under review on August 5 is a piece of something roughly twice that size.
The zoning that makes it possible came earlier too. A previous zone change referral, Z-25-116, applied an Incentive Zoning Overlay to the site. Incentive zoning is a trade: the applicant provides benefits or amenities to the community in exchange for adjustments to certain zoning requirements.
The county describes the possible amenities in this district as parks, utilities, preservation of farmland or open space, preservation of cultural, historic or other community facilities, and cash in lieu of amenities for specific identified purposes.
The amenities identified so far, per the staff report, are sewer infrastructure and a land trust.
### Three modifications, and the one with teeth
The board’s resolution lists three modifications the town must address before or as a condition of local approval.
The first is county roads. The Onondaga County Department of Transportation requires the applicant to keep coordinating with the department on North Hayes Road access plans, and the town must ensure any mitigation the department determines is reflected on the project plans.
The second is the state, and it is the one with a hard deadline attached. The New York State Department of Transportation requires continued coordination on required mitigation, specifically including the addition of turning lanes at the intersection of North Hayes Road, Hicks Road and Cold Springs Road. The town must ensure NYSDOT mitigation has been completed before the issuance of occupancy permits.
Read that again, because it is the practical constraint on the schedule. Not before construction. Before anyone is allowed to move in.
The third is sewers. For any sewer infrastructure built, the Onondaga County Department of Water Environment Protection requires engineer stamped plans and specifications for a sewer extension, plus capacity assurance review from WEP, the Onondaga County Health Department and the state Department of Environmental Conservation. Infrastructure must be designed at minimum to Ten State Standards.
WEP added two operating conditions. The developer must convey ownership of newly constructed public sewer infrastructure to WEP once the engineer certifies installation. And every new sewer connection requires an Onondaga County licensed plumber to apply for a plumbing permit through WEP’s Plumbing Control Division.

### What the county could not determine
The staff report is unusually direct about the gaps in the filing.
On parking, it describes what is drawn. Townhouse buildings have individual garages with three open lot spaces per cluster for visitors. Apartment buildings are paired around shared parking lots. Senior apartment buildings have large open parking between them plus surface parking along the driveway serving that area.
Then it says what is not there. Parking numbers for the individual apartment building lots and senior apartment building lots are not provided. The total number of proposed parking spaces is not provided. And it states plainly that it is unclear whether parking meets or exceeds municipal requirements.
For a 484 unit project, that is a substantial unknown sitting in the file.
On ownership, there is a second gap. Per an email with the town dated July 31, 2026, the internal roads will remain under private ownership, built to town specifications and maintained by a future homeowners association. But the staff report says future ownership of the townhouses, meaning owner occupied versus rental, is not clear at this time.
Whether 176 townhouses are for sale or for rent is not a small detail in a town’s housing picture. As of the county’s review, the answer was not in the paperwork.
On sidewalks, the report notes that sidewalks appear to connect the apartment and senior apartment buildings to their parking lots and run along at least one side of the internal road. But sidewalks are not shown connecting the townhouse buildings to the internal road sidewalks, a sidewalk covers only a small portion of the North Hayes Road frontage, and sidewalks do not appear to connect to Route 370 at all.
### The comments the board attached anyway
Beyond the three binding modifications, the board offered comments, which carry no legal force but signal what county planners want.
It advised the town to require all filed subdivision plans to include enough information to verify the parcels are buildable lots, including building setbacks, driveway access, proposed water and wastewater infrastructure, and any waterbodies, delineated wetlands or buffers, or other natural features of significance.
It urged the applicant to house stormwater basins on their own lots, and said responsibility for ownership and maintenance of stormwater management areas should be clearly established and funded.
And it encouraged good design of the neighborhoods, naming gathering spaces, a trail and sidewalk network, and transit stops, while minimizing the impact of parking.
That last comment reads differently next to the finding that the total parking count was missing.
### What happens next
County planning review under General Municipal Law Section 239 is advisory in form and consequential in practice. A recommended modification is not a veto. But when the county recommends modifications, a local board that wants to approve the project anyway faces a higher voting threshold under state law.
The decision belongs to Lysander. The town planning board is the referring board on this case, and it is the body that will act on the site plan.
Two access advisories also carry forward. Any driveway on North Hayes Road must meet Onondaga County Department of Transportation requirements. Any driveway on Route 370 must meet New York State Department of Transportation requirements. And any new roadway needs its street name reviewed and approved by the Onondaga County 911 Street Name Committee, a small item that tells you these are real streets being added to the county’s emergency response map.
Stormwater is also a live permit question. The preliminary site plan shows two stormwater management areas in the subject area, one in the northwest corner behind the apartment buildings and one along the North Hayes Road frontage between driveways. Because the wider project disturbs well over an acre, the state requires coverage under the SPDES permit program before the town approves anything.
For residents of Lysander, the number to hold onto is 484, and the intersection to watch is North Hayes, Hicks and Cold Springs. The state has already said turning lanes go in there before occupancy permits are issued. That is the clearest signal in the file about how much traffic the reviewing agencies expect this to generate.