Onondaga County is building a $36.6 million pump station and financing a $549.5 million wastewater plant expansion to serve the corridor where Micron’s semiconductor campus sits in the Town of Clay. County and state records show what each project does, what it costs, and whose money is paying for it.
Micron’s campus sits along Route 31 in the Town of Clay, in an area the county’s own capital plan describes as currently without public sewers. Two Onondaga County construction projects are building the infrastructure to fix that: a pump station nearing completion, and a much larger treatment plant expansion that won county bond approval late last year. Together the two add up to $586 million in county capital spending, according to the county’s adopted 2026-2031 Capital Improvement Plan and legislative hearing records.
This story came from public records we pulled ourselves
Get the next one, plus overnight incidents, in your inbox at 6 AM. Free, no spam.

A Pump Station for Ground That Had No Sewers
The White Pine Pump Station and Force Mains project is building a 5-million-gallon-a-day pump station and about 20,000 feet of new sewer force main, in 16-inch and 8-inch pipe, to serve what the county’s capital plan calls the White Pine Industrial Park: a 450-plus acre site along Route 31 and Caughdenoy Road owned by the county’s own Industrial Development Agency. Micron’s construction site sits inside that same corridor. A state authorization letter dated Jan. 6, 2026 lists the address for “Micron Campus Phase 1a” as White Pine Commerce Park, 5171 Route 31, Clay.
Construction on the pump station began in March 2025 and is due to finish in October 2026, according to the county Water Environment Protection department’s project page. The county’s capital plan puts the total cost at $36.6 million, financed through three separate legislative bond authorizations: $16 million in February 2022, another $19 million in February 2024 after engineers determined the project needed two force mains instead of one, and $1.6 million in cash approved in 2020 for engineering. WEP’s project page states the work is paid for through capital improvement funding and existing sewer user fee revenue, and adds that “no special assessment to residents is needed.”
The capital plan describes the pump station as one of the requirements the site needs before it can receive “Shovel-Ready Certification” from the state, a pre-permitting designation site-selection consultants use to judge whether a property is ready for major investment.
Tripling a Plant Built Around 1980
The larger project is at the Oak Orchard Wastewater Treatment Plant, also in the Town of Clay, which the county’s capital plan says was built around 1980 to treat an average of 10 million gallons of sewage a day. A NYSDEC environmental justification statement dated April 10, 2026 says the plant’s permitted discharge will grow to 30.8 million gallons a day “at full build-out,” more than triple its original design.
The same NYSDEC document explains why. It describes the expansion as serving “the Micron Semiconductor Manufacturing Project,” and lays out a water-recycling loop between the two sites. Treated wastewater from the plant’s upgraded municipal system would be piped to Micron as source water for the company’s ultrapure water system, the filing states, and treated water from a new industrial treatment system built specifically to handle Micron’s wastewater would be piped back to Micron for cooling. NYSDEC’s filing describes a new underground corridor connecting the treatment plant site to Micron’s campus to carry that water in both directions.
Onondaga County’s capital plan breaks the expansion into three pieces: an upgrade so the plant can treat higher flows, a new biosolids-processing facility using anaerobic digestion, and what the county calls a “bridging project,” interim work meant to keep the plant meeting its discharge permit while construction happens around it.
The Bond, and Who Actually Pays
The County Legislature has authorized $30 million for the project’s engineering phase since February 2022. A second and far larger request, to borrow up to $515 million more, went to a public hearing on Dec. 29, 2025. Written testimony filed with the Legislature ahead of that hearing quotes the resolution’s own language: it authorizes “the Issuance of $515,000,000 Bonds of the County of Onondaga, New York, to Pay Costs of Improvements for the Onondaga County Sanitary District.” Added to money already committed, the county’s capital plan puts the full project at $549.5 million, with spending scheduled at $119.5 million in 2026, $150 million in 2027 and $280 million in 2028. The plan lists the project’s phase as design and engineering.
Every dollar identified in county records for both projects is county-issued bond debt, not a direct payment from Micron. The White Pine project is also backed by existing sewer user fee revenue, and the county states outright that residents face no special assessment for it. For Oak Orchard, county residents who submitted written comments ahead of the December hearing called the $515 million bond the largest single project in county history, bigger than the $164 million Waste-to-Energy plant built in the 1990s or the $200-million-plus Metro plant upgrades from the mid-2000s, and pressed for more detail on how it would affect sewer rates before the vote. CNY Signal did not find a county rate-setting document confirming a specific dollar impact on ratepayer bills, so none is reported here. No document reviewed for this story states that Micron is directly funding construction of either project.
Nine Permits From the State, and a Separate Process for Water Lines
Apart from the county’s construction financing, NYSDEC said in a Dec. 12, 2025 release that it had issued nine environmental permits for the Micron project in Onondaga County. Those covered freshwater wetlands, threatened and endangered species, six associated wetland mitigation projects, and a Clean Water Act Section 401 water quality certificate. A draft air permit was still open for public comment at the time and had not been finalized. The same release noted that separate comment periods were open on “connected actions” to extend water and gas service to Micron’s main campus, meaning that extension is handled as its own regulatory process, apart from the nine permits already issued.
None of the documents reviewed for this story gave a date for when Micron plans to pour first concrete or start production. That is a company statement, not something that turned up in the county or state paperwork.
Sources
- Onondaga County 2026-2031 Adopted Capital Improvement Plan, Onondaga County Department of Finance, adopted December 2025. https://onondaga.gov/finance/wp-content/uploads/sites/193/2025/12/2026-2031-Capital-Improvement-Plan-Adopted-v2.pdf
- White Pine Pump Station and Force Mains project page, Onondaga County Water Environment Protection. https://onondaga.gov/wep/capital-improvements/project_highlights/2025-whitepine/
- “DEC Issues Nine Environmental Permits to Micron New York Semiconductor Manufacturing Project in Onondaga County,” New York State Department of Environmental Conservation, press release, Dec. 12, 2025. https://dec.ny.gov/news/press-releases/2025/12/dec-issues-nine-environmental-permits-to-micron-new-york-semiconductor-manufacturing-project-in-onondaga-county
- Letter of Authorization for SPDES General Permit for Stormwater Discharges from Construction Activity, Micron Campus Phase 1a, NYSDEC Division of Water, Jan. 6, 2026. https://dec.ny.gov/sites/default/files/2026-01/micronauthletter.pdf
- Oak Orchard Wastewater Treatment Plant, Justification Statement for Inconsistency with Section 7(2) of the Climate Leadership and Community Protection Act, NYSDEC, April 10, 2026. https://onondaga.gov/wep/wp-content/uploads/sites/219/2026/04/NYSDEC_Oak-Orchard_CLCPA-72-Justification_4.10.26.pdf
- Written public comments on the Oak Orchard Service Area WWTP Expansion bond resolution, Onondaga County Legislature, submitted ahead of the Dec. 29, 2025 public hearing. https://onondaga.gov/legislature/wp-content/uploads/sites/201/2026/01/12.29.25-Comments.pdf
Every figure in this story is drawn from the records above. Links go to the primary documents.