Cicero Gets 10 Days to Weigh In as Federal Route 31 and Route 11 Study Opens, Comments Due Aug. 14

9 min read
Route 31 approaching the Route 298 roundabout at Bridgeport in the town of Cicero, about two miles east of the federal study's South Bay Road limit. (Photo: 420Traveler / Wikimedia Commons, CC BY-SA 4.0; 2021)
In this story

    AI assisted, human edited local reporting. How this story was produced · Corrections

    In this story

      The Central New York Forward environmental review covers Route 31, Route 11, I-81 and Route 481 through Cicero and Clay. A final scoping meeting lands Aug. 6, and the federal comment window closes Aug. 14.

      Cicero Town Supervisor Rob Santucci calls it an announcement that “couldn’t come at a better time.” The Federal Highway Administration published a Notice of Intent on July 8, 2026 to prepare a full Environmental Impact Statement for a highway overhaul spanning four corridors through the towns of Cicero and Clay, and residents have until Friday, August 14 to tell the state what they want the project to become.

      This story came from public records we pulled ourselves

      Get the next one, plus overnight incidents, in your inbox at 6 AM. Free, no spam.

      The study, branded Central New York Forward, is the state’s most sweeping look yet at the roads that carry Cicero residents to work, school and Oneida Lake. Its limits read like a map of the town’s daily commute: State Route 31 from South Bay Road, designated County Route 208, west to Oswego Road, County Route 57, in Clay. U.S. Route 11 from Factory Street north to Mud Mill Road, County Route 17, in Cicero. Interstate 81 from its junction with Interstate 481, identified in project materials as the Exit 96 and Business Loop 81 interchange, north to the Bartell Road interchange. And Route 481 from its interchange with Route 11 in Cicero to its interchange with Route 31 in Clay.

      Governor Kathy Hochul announced the launch on July 10, two days after the federal notice appeared at 91 FR 42257 under docket number FHWA-2026-0793. The New York State Department of Transportation is running the environmental review jointly with FHWA, and the notice states the project’s purpose as addressing “existing and reasonably foreseeable transportation needs, including multimodal” travel across the study area.

      What that means on the ground is still an open question, and that is exactly the point of the next ten days.

      CNY Forward: The Study at a Glance Federal highway review covering Cicero and Clay Aug 14 Public comment deadline, 2026 Notice of Intent, 91 FR 42257 4 Corridors under study Rte 31, Rte 11, I 81, Rte 481 $100B+ Micron investment driving growth 50,000 NY jobs projected over 30 years 84,000 People projected to move to NY 76,000+ expected in Central New York Source: FHWA Notice of Intent, July 8, 2026 and Gov. Hochul release, July 10, 2026 | CNY Signal

      Three concepts on the table, no plan adopted

      At the first public scoping session at Clay Town Hall on July 30, NYSDOT presented three different transportation concepts for the corridors, according to Spectrum News Central New York, which covered the meeting that evening. No final plan has been adopted.

      “This is really to define our project limits and hear from the community and show them what we understand to be the traffic impacts,” Elizabeth Parmley, NYSDOT’s Region 3 regional director, told Spectrum News at the session.

      A second and final scoping meeting runs Thursday, August 6 at Clay Town Hall, 4401 State Route 31, in two sessions: 1 to 3 p.m. and 4 to 7 p.m. Residents who cannot make it in person can submit comments through CNYForward.com, through the federal docket at regulations.gov, by mail to the NYSDOT Region 3 CNY Forward Project Team at the State Office Building, 333 E. Washington Street, Syracuse, NY 13202, or in person at a community outreach office the state opened July 14 at 4483 State Route 31 in Clay. The office is staffed Tuesdays from 9 a.m. to 1 p.m. and Thursdays from 3 to 7 p.m.

      The environmental review will follow the standard federal sequence laid out on the project website: scoping now, then a Draft Environmental Impact Statement with its own public comment period and hearing, then a Final EIS and a Record of Decision. The August 14 deadline closes only the scoping window, the phase where residents can still shape what alternatives get studied at all.

      Why Cicero, why now

      The state is not being coy about the driver. Micron Technology is investing more than $100 billion in its semiconductor campus just over the town line in Clay, a project the company says will create 50,000 New York jobs over roughly three decades. State officials project the buildout will draw about 84,000 people to New York, more than 76,000 of them to the Central New York region. Those workers, and their trucks, deliveries and school runs, will move on Cicero’s roads.

      Santucci, in a statement released with the governor’s announcement, welcomed the study as “a welcome step in the development of two major roadways (Rte. 31 and Rte. 11) in the towns of Cicero and Clay.”

      “With the construction of the Micron chip facility nearby, we are pleased to hear of the NYS DOT and Federal Highway Administration’s proposal to help mitigate traffic and clear congestion that will affect our community and address the transportation needs of our growing community going forward,” Santucci said.

      The town he leads has been absorbing growth for decades. Cicero counted 31,435 residents in the 2020 Census across 48.28 square miles, a town that held fewer than 15,000 people in 1960 and 22,539 by 1970 as Syracuse’s northern suburbs filled in. The new study area strings together the town’s commercial spine on Route 31, the Route 11 strip running north toward Brewerton, and the two interstates that box the town in.

      Interstate 481 southbound in Cicero with power lines and light traffic
      Interstate 481 southbound past Exit 8 in Cicero, one of the corridors in the Central New York Forward study. (Photo: Wikimedia Commons, CC BY-SA 4.0; July 2023)

      State Senator Rachel May, who represents part of the study area, framed the review as a hedge against what is coming. “As Central New York grows with Micron’s investment, we know traffic will grow right along with it,” May said in the July 10 announcement. “That’s why it’s so important to understand how increased traffic will affect our roads and communities and to plan ahead.”

      State Senator Christopher J. Ryan pointed at the daily stakes for people already here: “These improvements will help reduce traffic, improve safety, strengthen connections for workers traveling to job sites, and make it easier for residents to get to work, school and local businesses,” he said in the same release.

      The state has been chipping at Route 31 for five years

      Cicero drivers have seen this movie in miniature. In July 2021, NYSDOT went to the public with a $6.2 million package of Route 31 fixes: a mill and overlay of the pavement between Cicero North Syracuse High School and South Bay Road, a rebuilt signal with a dedicated left turn lane at South Bay Road, and a $2.2 million roundabout at the Thompson Road and Torchwood Lane intersection, according to Eagle News Online’s coverage of that comment period, which closed July 30, 2021.

      By April 2024, the price had grown to $8.3 million, CNY Central reported, with utility work underway, roundabout construction slated for 2025 and completion expected by the end of that year. The 2024 scope included the new sidewalk on the south side of Route 31, a safety add aimed at students walking to the high school that sits directly on the corridor.

      Central New York Forward is a different animal. Rather than rebuilding one intersection cluster, the EIS will study the whole network at once, with stated goals that include improving traffic operations and safety, cutting commercial truck traffic on residential streets, adding accommodations for pedestrians, cyclists and transit, and dealing with aging bridge infrastructure across the four corridors.

      Five Years From One Roundabout to a Full Review How the state’s Cicero highway work grew into CNY Forward Jul 2021 $6.2M Rte 31 plan, Thompson roundabout Mar 2024 Micron EIS notice filed for Clay campus Apr 2024 Rte 31 work grows to $8.3M Jul 8, 2026 FHWA notice opens CNY Forward EIS Jul 30 + Aug 6 Scoping meetings, Clay Town Hall Aug 14, 2026 Scoping comments due to FHWA Source: 91 FR 42257 (7/8/26); Eagle News (7/20/21); CNY Central (4/30/24) | CNY Signal

      The Micron review next door set the template

      The process will feel familiar to anyone who tracked the Micron campus itself. FHWA’s transportation notice follows the March 5, 2024 federal Notice of Intent that opened the Environmental Impact Statement for the Micron Semiconductor Manufacturing Facility Project in Clay, the review that preceded site work at White Pine Commerce Park. The transportation study is the infrastructure sequel: the state committing, on paper and in public, to figure out how the surrounding road network handles what the chip fab brings.

      Onondaga County Executive Ryan McMahon urged residents to treat the scoping window as a real lever. “As this planning continues, community voices will play an important role,” McMahon said in the launch announcement. “We encourage residents and businesses to stay engaged, share their ideas and help shape a transportation system that reflects our region’s ambitions and values.”

      Representative John W. Mannion, whose district covers the study area, was more direct about the moment: “The decisions we make today will shape Central New York and every voice should be part of that conversation,” he said, encouraging residents to visit the website, stop by the outreach office or attend the public meetings.

      What the Study Covers, Corridor by Corridor Official limits from the CNY Forward project materials Route 31 South Bay Road (CR 208), Cicero, to Oswego Road (CR 57), Clay US Route 11 Factory Street to Mud Mill Road (CR 17), both in Cicero Interstate 81 Exit 96 / Business Loop 81 interchange north to Bartell Road, Cicero Route 481 Route 11 interchange, Cicero, to Route 31 interchange, Clay Source: CNYForward.com project limits and Gov. Hochul release, July 10, 2026 | CNY Signal

      What Cicero residents should watch for

      Three things matter between now and mid August. First, the alternatives: the three concepts NYSDOT showed on July 30 are drafts, and scoping comments can add options or kill them. Second, the boundaries: Parmley said the agency is still defining project limits, which means a well argued comment about a left turn backup on Route 31 or truck cut through traffic on a residential street can literally move the lines of the study. Third, the record: every comment filed by August 14 goes into the federal docket, FHWA-2026-0793, and the agencies are required to respond to substantive scoping input in the Draft EIS.

      For a town that watched a single roundabout take four years from public meeting to construction, the timeline ahead is long. The EIS must pass through a draft, a formal hearing, a final version and a Record of Decision before a shovel touches Route 31. But the shape of all of it is being set right now, in a town hall on Route 31 and a comment box on a state website.

      The last in person chance is Thursday, August 6, at Clay Town Hall, 4401 State Route 31, from 1 to 3 p.m. and again from 4 to 7 p.m. Written comments are due Friday, August 14.

      Sources & Verification

      • Federal Highway Administration, Notice of Intent To Prepare an Environmental Impact Statement, Onondaga County, New York, 91 FR 42257, docket FHWA-2026-0793, published July 8, 2026. https://www.federalregister.gov/documents/2026/07/08/2026-13794/notice-of-intent-to-prepare-an-environmental-impact-statement-onondaga-county-new-york
      • Office of Governor Kathy Hochul, “Governor Hochul Announces Launch of Central New York Forward Project,” press release, July 10, 2026. https://www.governor.ny.gov/news/governor-hochul-announces-launch-central-new-york-forward-project-address-future
      • NYSDOT and FHWA, Central New York Forward project website, corridor limits and EIS process, accessed August 4, 2026. https://cnyforward.com/
      • Spectrum News Central New York, “State DOT hosts Central New York Forward public scoping meetings,” July 30, 2026. https://spectrumlocalnews.com/nys/central-ny/news/2026/07/31/state-dot-hosts-central-new-york-forward-public-scoping-meetings
      • CNY Central, “Key road projects in Syracuse and Cicero soon underway,” April 30, 2024. https://cnycentral.com/news/local/key-transit-projects-in-syracuse-and-cicero-soon-underway-i-81-viaduct-project-highway-cicero-north-syracuse-high-school-route-31
      • Eagle News Online, “Cicero: NYSDOT seeks public feedback on Route 31-Thompson roundabout,” July 20, 2021. https://www.eaglenewsonline.com/news/government/cicero-nysdot-seeks-public-feedback-on-route-31-thompson-roundabout/article_fd0a730b-f60f-5738-91ed-a3bdab226bf8.html
      • Federal Highway Administration, Notice of Intent, Micron Semiconductor Manufacturing Facility Project, Town of Clay, March 5, 2024. https://www.federalregister.gov/documents/2024/03/05/2024-04709/notice-of-intent-to-prepare-an-environmental-impact-statement-for-the-micron-semiconductor
      • U.S. Census Bureau 2020 Census figures for the Town of Cicero, as compiled at https://en.wikipedia.org/wiki/Cicero,_New_York

      Reporter: Matt Keenan. Edited by: the CNY Signal news team. Published: August 4, 2026.

      Know someone who should see this?

      Every share helps CNY stay informed. Post it to your neighborhood group, text it to a friend, or drop it on Reddit.

      M

      Transportation and Infrastructure Reporter

      Matt Keenan

      Covers transportation and infrastructure across Central New York, including New York State Department of Transportation projects on Interstate 81, Route 481, and Route 690.


      Last updated  · Corrections policy